Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 14-329-15-50 07-1W0804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-VEN-23-20.9/24.2 Federal Project: NONE Progress payment No. 09 Payment period ending: 10-01-14 GRANITE CONSTRUCTION COMPANY P O BOX 742478 LOS ANGELES, CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,196,247.46 2,250.22 2.a. Extra Work 56,454.12 0.00 b. Adjustment Comp. 45,547.85 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,298,249.43 2,250.22 5. Mobilization 126,765.00 0.00 6. Total Work Completed 1,425,014.43 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,425,014.43 12,250.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,250.22