Dept. of Trans. PROGRESS Serial No. Contract No. 15-173-10-51 07-1W0904 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 33% Location: Federal Project: 07-VEN-23-17.8/20.9 NONE Progress payment No. 001 Payment period ending: 06-20-15 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 849,454.28 849,454.28 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 849,454.28 849,454.28 5. Mobilization 110,000.00 110,000.00 6. Total Work Completed 959,454.28 7. Deductions -16,843.51 -16,843.51 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 942,610.77 942,610.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 942,610.77