Dept. of Trans. FINAL Serial No. Contract No. 15-328-16-54 07-1W0904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-VEN-23-17.8/20.9 NONE Progress payment No. 003 Payment period ending: 07-21-15 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 905,546.29 0.00 2. a. Extra Work b. Adustment Comp. -86,223.17 -86,223.17 3. Materials on Hand 4. Earned Subject to Retention 819,323.12 -86,223.17 5. Mobilization 110,000.00 0.00 6. Total Work Completed 929,323.12 7. Deductions 0.00 96,223.71 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 929,323.12 10,000.54 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.54