Dept. of Trans. PROGRESS Serial No. Contract No. 15-355-13-02 07-1W2204 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 40% Location: Federal Project: 07-LA-10-18.5 NONE Progress payment No. 005 Payment period ending: 12-20-15 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 751,564.41 53,610.44 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 751,564.41 53,610.44 5. Mobilization 43,700.00 0.00 6. Total Work Completed 795,264.41 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 795,264.41 53,610.44 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 53,610.44