Dept. of Trans. PROGRESS Serial No. Contract No. 14-147-10-33 07-1W4004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 93% 07-LA-405 Federal Project: NONE Progress payment No. 08 Payment period ending: 05-20-14 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE, CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 890,670.70 299,787.06 2.a. Extra Work 71,347.78 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 962,018.48 299,787.06 5. Mobilization 116,000.00 5,800.00 6. Total Work Completed 1,078,018.48 7. Deductions -17,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. -84,901.91 -29,978.71 c. Reduction after 95% Comp. 9. Total pay to Contractor 976,116.57 275,608.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 275,608.35