Dept. of Trans. PROGRESS Serial No. Contract No. 13-263-08-29 07-1W4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 97% 07-LA-10-3.9/13.9 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-20-13 HIGHLAND CONSTRUCTION INC 133 N PIXLEY STREET ORANGE, CA 92868 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 167,711.10 8,400.00 2.a. Extra Work 4,800.00 0.00 b. Adjustment Comp. 12,471.74 6,753.38 3. Materials on Hand 4. Earned Subject to Retention 184,982.84 15,153.38 5. Mobilization 20,000.00 0.00 6. Total Work Completed 204,982.84 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 6,820.35 c. Reduction after 95% Comp. 9. Total pay to Contractor 204,982.84 21,973.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,973.73