Dept. of Trans. PROGRESS Serial No. Contract No. 16-145-08-13 07-1W5104 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 83% Location: Federal Project: 07-LA-1-44.4/44.4 NONE Progress payment No. 005 Payment period ending: 05-20-16 FLEMING ENVIRONMENTAL INC 1372 EAST VALENCIA DR FULLERTON CA 92831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 559,040.75 16,815.67 2. a. Extra Work 74,646.81 42,323.63 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 633,687.56 59,139.30 5. Mobilization 6. Total Work Completed 633,687.56 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 633,687.56 59,139.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 59,139.30