Dept. of Trans. PROGRESS Serial No. Contract No. 13-354-13-22 07-1W5304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 82% 07-VEN-23-6.0/6.0 Federal Project: NONE Progress payment No. 06 Payment period ending: 12-20-13 AUTOBAHN CONSTRUCTION INC P O BOX 11238 SANTA ANA CA 927111238 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 474,068.45 512.00 2.a. Extra Work 32,680.91 8,220.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 506,749.36 8,732.00 5. Mobilization 60,000.00 0.00 6. Total Work Completed 566,749.36 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 566,749.36 8,732.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,732.00