Dept. of Trans. PROGRESS Serial No. Contract No. 14-056-11-50 07-1W5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 48% 07-LA-107-2.1/3.7 Federal Project: NONE Progress payment No. 04 Payment period ending: 02-20-14 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 952,259.93 49,058.08 2.a. Extra Work 1,566.71 1,566.71 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 953,826.64 50,624.79 5. Mobilization 7,000.00 0.00 6. Total Work Completed 960,826.64 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 960,826.64 50,624.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 50,624.79