Dept. of Trans. PROGRESS Serial No. Contract No. 15-054-14-09 07-1W5904 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 0% Location: Federal Project: 07-LA-10-40.5/40.5 NONE Progress payment No. 005 Payment period ending: 02-20-15 VELARDE CONCRETE CONSTRUCTION INC 523 S BRAND BLVD #201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 824,198.73 318,997.59 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 45,904.59 0.00 4. Earned Subject to Retention 870,103.32 318,997.59 5. Mobilization 52,000.00 2,600.00 6. Total Work Completed 876,198.73 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 922,103.32 321,597.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 321,597.59