Dept. of Trans. PROGRESS Serial No. Contract No. 14-297-10-50 07-1W6104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 37% 07-LA-91-6.0/21.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-20-14 VELARDE CONCRETE CONSTRUCTION INC 523 S BRAND BLVD SUITE 201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 621,983.25 298,840.35 2.a. Extra Work 27,871.02 7,603.98 b. Adjustment Comp. 3. Materials on Hand 7,908.35 0.00 4. Earned Subject to Retention 657,762.62 306,444.33 5. Mobilization 40,000.00 2,000.00 6. Total Work Completed 689,854.27 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 697,762.62 308,444.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 308,444.33