Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-10-16 07-1W6104 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 37% Location: Federal Project: 07-LA-91-6.0/21.0 NONE Progress payment No. 004 Payment period ending: 03-20-15 VELARDE CONCRETE CONSTRUCTION INC 523 S BRAND BLVD SUITE 201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 644,667.10 22,683.85 2. a. Extra Work 33,593.58 5,722.56 b. Adustment Comp. 3. Materials on Hand 0.00 -7,908.35 4. Earned Subject to Retention 678,260.68 20,498.06 5. Mobilization 40,000.00 0.00 6. Total Work Completed 718,260.68 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 718,260.68 20,498.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 20,498.06