Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-119-13-32 07-1W6304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-2-14.5/R23.2 NONE Progress payment No. 006 Payment period ending: 01-21-15 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 723,254.41 0.00 2. a. Extra Work 98,739.75 98,739.75 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 821,994.16 98,739.75 5. Mobilization 27,000.00 0.00 6. Total Work Completed 848,994.16 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 848,994.16 108,739.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,739.75