Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 16-152-13-11 07-1W6404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-14-24.8/69.0 NONE Progress payment No. 010 Payment period ending: 04-22-16 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 777,553.89 0.00 2. a. Extra Work 1,651.16 0.00 b. Adustment Comp. 2,450.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 781,655.05 0.00 5. Mobilization 60,000.00 0.00 6. Total Work Completed 841,655.05 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 841,655.05 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00