Dept. of Trans. FINAL Serial No. Contract No. 16-105-09-09 07-1W6504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-101-2.9/21.0 NONE Progress payment No. 010 Payment period ending: 06-30-15 SUN CONSTRUCTION GROUP INC 3151 AIRWAY AVE #V COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 926,725.59 0.00 2. a. Extra Work 29,890.53 0.00 b. Adustment Comp. 10,547.97 10,547.97 3. Materials on Hand 4. Earned Subject to Retention 967,164.09 10,547.97 5. Mobilization 6,000.00 0.00 6. Total Work Completed 973,164.09 7. Deductions -35,646.54 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 937,517.55 10,547.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,547.97