Dept. of Trans. PROGRESS Serial No. Contract No. 14-325-14-12 07-1W6904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 23% 07-LA-72-0.0/6.8 Federal Project: NONE Progress payment No. 01 Payment period ending: 11-20-14 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 118,257.34 118,257.34 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 118,257.34 118,257.34 5. Mobilization 42,400.00 42,400.00 6. Total Work Completed 160,657.34 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 160,657.34 160,657.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 160,657.34