Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 03-220-15-05 07-1X1404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 99% 07-LA-1-42.5/ .0 Federal Project: ACST-P001(494) P-P001(494) Progress payment No. 04 Payment period ending: 08-08-03 S P PAZARGAD ENGINEERING CONSTRUCTION INC 5921 WISH AVENUE ENCINO CA 91316 Escrow No. 02059 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,172.50 0.00 2.a. Extra Work 23,932.42 16,971.90 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 42,104.92 16,971.90 5. Mobilization 6. Total Work Completed 42,104.92 7. Deductions -8,450.00 0.00 8. a.Contract Retentions -4,210.49 -1,697.19 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 29,444.43 15,274.71 10. Reduction Amt to Escrow 11. Payment to Escrow 4,210.00 12. Net Pymt. this Estimate 15,274.71