Dept. of Trans. PROGRESS Serial No. Contract No. 03-237-12-42 07-1X1404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 100% 07-LA-1-42.5/ .0 Federal Project: ACST-P001(494) P-P001(494) Progress payment No. 05 Payment period ending: 08-20-03 S P PAZARGAD ENGINEERING CONSTRUCTION INC 5921 WISH AVENUE ENCINO CA 91316 Escrow No. 02059 Total Estimate This Estimate 1. Contract Itms Without Mobil. 56,107.39 37,934.89 2.a. Extra Work 155,658.04 131,725.62 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 211,765.43 169,660.51 5. Mobilization 113,819.63 113,819.63 6. Total Work Completed 325,585.06 7. Deductions -35,469.62 -27,019.62 8. a.Contract Retentions -21,176.54 -16,966.05 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 268,938.90 239,494.47 10. Reduction Amt to Escrow 11. Payment to Escrow 21,170.00 12. Net Pymt. this Estimate 239,494.47