Dept. of Trans. PROGRESS Serial No. Contract No. 10-265-09-53 07-1X3214 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 74% 07-LA-39-40.0/44.4 Federal Project: ER-4137(4) Progress payment No. 06 Payment period ending: 09-20-10 JOHN S MEEK COMPANY INC 14732 S MAPLE AVENUE GARDENA CA 90248 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,090,846.50 191,766.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 120,451.93 -21,248.07 4. Earned Subject to Retention 1,211,298.43 170,518.43 5. Mobilization 118,750.00 0.00 6. Total Work Completed 1,209,596.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,330,048.43 170,518.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 170,518.43