Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-286-08-35 07-1X3804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-5-42.6/88.6 Federal Project: NONE Progress payment No. 06 Payment period ending: 09-14-06 ALLIED PAVING COMPANY 1234 N. BLUE GUM ST. ANAHEIM, CA 92806 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,250.00 0.00 2.a. Extra Work 973,000.75 13,008.24 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 981,250.75 13,008.24 5. Mobilization 6. Total Work Completed 981,250.75 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 981,250.75 13,008.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,008.24