Dept. of Trans. FINAL Serial No. Contract No. 18-121-14-06 07-1XE204 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-5-35.0/47.1 NONE 07-LA-210-7.0/7.0 Progress payment No. 007 Payment period ending: 02-28-18 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,925.00 0.00 2. a. Extra Work 356,994.95 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 359,919.95 0.00 5. Mobilization 6. Total Work Completed 359,919.95 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 359,919.95 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00