Dept. of Trans. PROGRESS Serial No. Contract No. 19-085-09-44 07-1XE304 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 100% Location: Federal Project: 07-LA-5-588.0/81.8 NONE 07-LA-210-8.0/0.8 Progress payment No. 001 Payment period ending: 03-20-19 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 76,851.87 76,851.87 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 76,851.87 76,851.87 5. Mobilization 6. Total Work Completed 76,851.87 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 76,851.87 76,851.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 76,851.87