Dept. of Trans. PROGRESS Serial No. Contract No. 18-236-09-29 07-1XF904 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 99% Location: Federal Project: 07-VEN-1-0.7/0.8 NONE Progress payment No. 005 Payment period ending: 08-20-18 BALTAZAR CONSTRUCTION, INC 236 E. ARROW HWY COVINA CA 91722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 120,227.65 7,650.64 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 120,227.65 7,650.64 5. Mobilization 6. Total Work Completed 120,227.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 120,227.65 7,650.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,650.64