Dept. of Trans. PROGRESS Serial No. Contract No. 18-206-09-49 07-1XG404 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 60% Location: Federal Project: 07-LA-5-54.1 NONE 07-LA-126-5.6/5.6 Progress payment No. 002 Payment period ending: 07-20-18 IBARRA GENERAL ENGINEERING INC 4325 TYROLITE ST RIVERSIDE CA 92509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 431,218.06 267,693.82 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 431,218.06 267,693.82 5. Mobilization 6. Total Work Completed 431,218.06 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 431,218.06 267,693.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 267,693.82