Dept. of Trans. PROGRESS Serial No. Contract No. 18-206-11-20 07-1XG704 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 21% Location: Federal Project: 07-VEN-33-13.2/30.5 NONE Progress payment No. 001 Payment period ending: 07-20-18 AZ CONSTRUCTION INC 727 GLENDORA AVE LA PUENTE CA 91744 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 51,177.50 51,177.50 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 51,177.50 51,177.50 5. Mobilization 6. Total Work Completed 51,177.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 51,177.50 51,177.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,177.50