Dept. of Trans. PROGRESS Serial No. Contract No. 21-082-08-37 07-1XM604 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 100% Location: Federal Project: 07-LA-5-0.0 NONE Progress payment No. 009 Payment period ending: 03-20-21 FERREIRA CONSTRUCTION CO INC 10370 COMMERCE CENTER DR #B-2 RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 486,304.21 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 486,304.21 0.00 5. Mobilization 6. Total Work Completed 486,304.21 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 486,304.21 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00