Dept. of Trans. FINAL Serial No. Contract No. 21-333-16-18 07-1XM604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-LA-5-0.0 NONE Progress payment No. 012 Payment period ending: 05-21-21 FERREIRA CONSTRUCTION CO INC 10370 COMMERCE CENTER DR #B-2 RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,431.00 0.00 2. a. Extra Work 494,421.84 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 498,852.84 0.00 5. Mobilization 6. Total Work Completed 498,852.84 7. Deductions 0.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 498,852.84 2,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,000.00