Dept. of Trans. SEMI-FINAL Serial No. Contract No. 20-069-08-36 07-1XN504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 07-VEN-150-17.9/17.9 NONE Progress payment No. 006 Payment period ending: 01-27-20 SUMMER CONSTRUCTION INC 15245 TELEGRAPH RD SANTA PAULA CA 93060 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,500.00 0.00 2. a. Extra Work 669,956.61 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 685,456.61 0.00 5. Mobilization 6. Total Work Completed 685,456.61 7. Deductions 0.00 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 685,456.61 3,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,000.00