Dept. of Trans. PROGRESS Serial No. Contract No. 20-328-12-18 07-1XP004 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 100% Location: Federal Project: 07-LA-5-42.6/47.9 NONE 07-LA-14-24.8/24.8 Progress payment No. 008 Payment period ending: 11-20-20 ALCORN FENCE COMPANY 9901 GLENOAKS BLVD SUN VALLEY CA 91352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 445,675.45 949.85 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 445,675.45 949.85 5. Mobilization 6. Total Work Completed 445,675.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 445,675.45 949.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 949.85