Dept. of Trans. PROGRESS Serial No. Contract No. 20-057-14-05 07-1XP104 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 30% Location: Federal Project: 07-LA-5-42.6/47.9 NONE 07-LA-14-24.8/27.0 07-LA-210-0.0/1.9 Progress payment No. 002 Payment period ending: 02-20-20 BALTAZAR CONSTRUCTION, INC 236 E. ARROW HWY COVINA CA 91722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 444,851.70 164,662.79 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 444,851.70 164,662.79 5. Mobilization 6. Total Work Completed 444,851.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 444,851.70 164,662.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 164,662.79