Dept. of Trans. PROGRESS Serial No. Contract No. 20-267-10-47 07-1XP404 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 67% Location: Federal Project: 07-LA-14-35.7/39.8 NONE Progress payment No. 006 Payment period ending: 09-20-20 MANERI TRAFFIC CONTROL INC 4949 SECOND ST FALLBROOK CA 92028 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 751,712.30 82,548.42 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 751,712.30 82,548.42 5. Mobilization 6. Total Work Completed 751,712.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 751,712.30 82,548.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,548.42