Dept. of Trans. PROGRESS Serial No. Contract No. 21-055-10-53 07-1XQ504 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 100% Location: Federal Project: 07-VEN-0-0.0 NONE Progress payment No. 006 Payment period ending: 02-20-21 SPECTRUM CONSTRUCTION GROUP INC 16 GOODYEAR #140 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 340,940.66 7,710.35 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 340,940.66 7,710.35 5. Mobilization 6. Total Work Completed 340,940.66 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 330,940.66 7,710.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,710.35