Dept. of Trans. PROGRESS Serial No. Contract No. 22-356-14-48 07-1XW204 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 60% Location: Federal Project: 07-LA-10-135.0/15.6 NONE 07-LA-110-216.0/21.6 Progress payment No. 002 Payment period ending: 12-20-22 POWELL CONSTRUCTORS INC 8555 BANANA AVE FONTANA CA 92335 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 470,094.15 30,181.24 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 470,094.15 30,181.24 5. Mobilization 6. Total Work Completed 470,094.15 7. Deductions 0.00 8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 470,094.15 38,181.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,181.24