Dept. of Trans. PROGRESS Serial No. Contract No. 22-332-14-55 07-1XY304 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 91% Location: Federal Project: 07-LA-110-66.0/7.4 NONE Progress payment No. 003 Payment period ending: 11-20-22 ORNELAS CONSTRUCTION, INC 1024 N MACLAY AVENUE #J SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 98,190.71 598.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 98,190.71 598.00 5. Mobilization 6. Total Work Completed 98,190.71 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 98,190.71 598.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 598.00