Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 02-210-10-56 07-1Y1704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-138-2.0/15.0 Federal Project: NONE Progress payment No. 09 Payment period ending: 06-24-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 790,510.44 22,538.60 2.a. Extra Work 125,050.29 0.00 b. Adjustment Comp. -11,591.43 -11,591.43 3. Materials on Hand 4. Earned Subject to Retention 903,969.30 10,947.17 5. Mobilization 6. Total Work Completed 903,969.30 7. Deductions -2,000.00 -2,000.00 8. a.Contract Retentions -44,651.11 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 44,651.11 44,651.11 9. Total pay to Contractor 901,969.30 53,598.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 53,598.28