Dept. of Trans. PROGRESS Serial No. Contract No. 06-268-13-45 07-1Y5304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 47% 07-LA-164-4.0/4.8 Federal Project: NONE Progress payment No. 01 Payment period ending: 09-20-06 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 928782229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 357,192.30 357,192.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 357,192.30 357,192.30 5. Mobilization 18,000.00 18,000.00 6. Total Work Completed 375,192.30 7. Deductions 8. a.Contract Retentions -17,859.62 -17,859.62 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 357,332.68 357,332.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 357,332.68