Dept. of Trans. PROGRESS Serial No. Contract No. 07-081-14-35 07-1Y6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 100% 07-LA-91-9.8/10.0 Federal Project: NONE Progress payment No. 08 Payment period ending: 03-20-07 PK CONSTRUCTION 2126 N FAIR OAKS ALTADENA CA 91001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 133,740.50 41,860.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 46,156.25 0.00 4. Earned Subject to Retention 179,896.75 41,860.00 5. Mobilization 23,750.00 0.00 6. Total Work Completed 157,490.50 7. Deductions -22,754.06 -22,004.06 8. a.Contract Retentions -8,994.84 -723.04 b. Unsatisfactory Prog. -6,888.49 -2,093.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 165,009.36 17,039.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,039.90