Dept. of Trans. PROGRESS Serial No. Contract No. 07-172-10-02 07-1Y7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 100% 07-LA-47-0.8/2.0 Federal Project: NONE Progress payment No. 07 Payment period ending: 06-20-07 CHRISTIE CONSTRUCTORS INC 4925 SEAPORT AVENUE RICHMOND CA 94804 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 706,276.00 104,377.00 2.a. Extra Work 169,680.61 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 875,956.61 104,377.00 5. Mobilization 98,000.00 0.00 6. Total Work Completed 973,956.61 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -43,797.83 -5,218.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 910,158.78 99,158.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 99,158.15