Dept. of Trans. PROGRESS Serial No. Contract No. 05-327-13-12 07-1Y7204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 93% 07-LA-405-13.0/13.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-20-05 ODONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 02202 Total Estimate This Estimate 1. Contract Itms Without Mobil. 491,961.50 280,909.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 491,961.50 280,909.00 5. Mobilization 70,000.00 3,500.00 6. Total Work Completed 561,961.50 7. Deductions 8. a.Contract Retentions -24,598.08 -10,349.43 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 537,363.42 274,059.57 10. Reduction Amt to Escrow 11. Payment to Escrow 24,590.00 12. Net Pymt. this Estimate 274,059.57