Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-159-11-56 07-1Y7204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-405-13.0/13.0 Federal Project: NONE Progress payment No. 11 Payment period ending: 05-25-06 ODONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 02202 Total Estimate This Estimate 1. Contract Itms Without Mobil. 738,767.50 23,230.00 2.a. Extra Work 185,957.94 3,632.21 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 924,725.44 26,862.21 5. Mobilization 70,000.00 0.00 6. Total Work Completed 994,725.44 7. Deductions 8. a.Contract Retentions -44,893.16 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 44,893.16 44,893.16 9. Total pay to Contractor 994,725.44 71,755.37 10. Reduction Amt to Escrow -44,890.00 -44,890.00 11. Payment to Escrow 44,890.00 12. Net Pymt. this Estimate 26,865.37