Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-310-08-57 07-1Y8204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-138-2.2/4.3 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-06 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 788,217.55 3,693.80 2.a. Extra Work 55,835.46 5,939.71 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 844,053.01 9,633.51 5. Mobilization 16,400.00 0.00 6. Total Work Completed 860,453.01 7. Deductions -20,000.00 -20,000.00 8. a.Contract Retentions -41,720.98 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 41,720.98 41,720.98 9. Total pay to Contractor 840,453.01 31,354.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,354.49