Dept. of Trans. PROGRESS Serial No. Contract No. 05-236-13-38 07-1Y8604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 4% 69% 07-LA-101-0.0/1.8 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-05 AMERICA WEST LANDSCAPE INC P O BOX 1698 BELLFLOWER CA 90707 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,433.14 12,433.14 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 12,433.14 12,433.14 5. Mobilization 6. Total Work Completed 12,433.14 7. Deductions 8. a.Contract Retentions -1,243.31 -1,243.31 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,189.83 11,189.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,189.83