Dept. of Trans. PROGRESS Serial No. Contract No. 05-297-14-49 07-1Y8604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 100% 07-LA-101-0.0/1.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-20-05 AMERICA WEST LANDSCAPE INC P O BOX 1698 BELLFLOWER CA 90707 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 238,969.40 94,826.40 2.a. Extra Work 12,206.11 12,206.11 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 251,175.51 107,032.51 5. Mobilization 12,569.68 628.48 6. Total Work Completed 263,745.19 7. Deductions 8. a.Contract Retentions -12,558.78 -5,351.63 b. Unsatisfactory Prog. -11,937.11 -5,351.62 c. Reduction after 95% Comp. 9. Total pay to Contractor 239,249.30 96,957.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 96,957.74