Dept. of Trans. PROGRESS Serial No. Contract No. 05-327-14-48 07-1Y8604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-101-0.0/1.8 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-20-05 AMERICA WEST LANDSCAPE INC P O BOX 1698 BELLFLOWER CA 90707 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 244,476.43 5,507.03 2.a. Extra Work 13,689.28 1,483.17 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 258,165.71 6,990.20 5. Mobilization 12,569.68 0.00 6. Total Work Completed 270,735.39 7. Deductions 8. a.Contract Retentions -12,908.29 -349.51 b. Unsatisfactory Prog. 0.00 11,937.11 c. Reduction after 95% Comp. 9. Total pay to Contractor 257,827.10 18,577.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,577.80