Dept. of Trans. PROGRESS Serial No. Contract No. 05-145-11-09 07-200704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 57% 07-VEN-34-6.3/17.7 Federal Project: ACST-P034(3) PHG-P034(3) Progress payment No. 02 Payment period ending: 05-20-05 CHRISP COMPANY P O BOX 1368 FREMONT CA 94539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 442,188.04 435,488.04 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 442,188.04 435,488.04 5. Mobilization 15,900.00 15,900.00 6. Total Work Completed 458,088.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 458,088.04 451,388.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 451,388.04