Dept. of Trans. PROGRESS Serial No. Contract No. 06-082-08-30 07-201204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 42% 07-LA-405-38.7/39.4 Federal Project: ACNH-405-3(50) I-405-3(50) Progress payment No. 14 Payment period ending: 03-20-06 STEVE P RADOS INC P O BOX 15128 SANTA ANA CA 927350128 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,495,544.48 662,112.58 2.a. Extra Work 139,089.38 187.60 b. Adjustment Comp. 600,000.00 0.00 3. Materials on Hand 220,052.49 10,209.28 4. Earned Subject to Retention 11,454,686.35 672,509.46 5. Mobilization 2,232,500.00 0.00 6. Total Work Completed 13,467,133.86 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,687,186.35 672,509.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 672,509.46