Dept. of Trans. PROGRESS Serial No. Contract No. 06-326-15-14 07-201204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 71% 07-LA-405-38.7/39.4 Federal Project: ACNH-405-3(50) I-405-3(50) Progress payment No. 22 Payment period ending: 11-20-06 STEVE P RADOS INC P O BOX 15128 SANTA ANA CA 927350128 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,030,719.46 499,403.45 2.a. Extra Work 288,640.76 43,552.92 b. Adjustment Comp. 653,296.17 47,262.98 3. Materials on Hand 512,783.10 84,814.43 4. Earned Subject to Retention 16,485,439.49 675,033.78 5. Mobilization 2,350,000.00 0.00 6. Total Work Completed 18,322,656.39 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,835,439.49 675,033.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 675,033.78