Dept. of Trans. PROGRESS Serial No. Contract No. 06-206-11-31 07-201604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 5% 18% 07-LA-5707 Federal Project: NONE Progress payment No. 06 Payment period ending: 07-20-06 MEPCO SERVICES INC 9634 WASHBURN ROAD UNIT B DOWNEY CA 90241 Escrow No. 02213 Total Estimate This Estimate 1. Contract Itms Without Mobil. 249,050.00 77,800.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 249,050.00 77,800.00 5. Mobilization 6. Total Work Completed 249,050.00 7. Deductions -3,250.00 0.00 8. a.Contract Retentions -24,905.00 -7,780.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 220,895.00 70,020.00 10. Reduction Amt to Escrow 11. Payment to Escrow 24,900.00 12. Net Pymt. this Estimate 70,020.00