Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-11-18 07-201604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 90% 07-LA-5707 Federal Project: NONE Progress payment No. 30 Payment period ending: 06-20-08 MEPCO SERVICES INC 9634 WASHBURN ROAD UNIT B DOWNEY CA 90241 Escrow No. 02213 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,104,740.00 177,060.00 2.a. Extra Work 42,876.35 0.00 b. Adjustment Comp. 127,011.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,274,627.35 177,060.00 5. Mobilization 6. Total Work Completed 3,274,627.35 7. Deductions -6,500.00 -3,250.00 8. a.Contract Retentions -163,731.37 -8,853.00 b. Unsatisfactory Prog. -28,108.50 -8,853.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 3,076,287.48 156,104.00 10. Reduction Amt to Escrow 11. Payment to Escrow 163,730.00 12. Net Pymt. this Estimate 156,104.00