Dept. of Trans. PROGRESS Serial No. Contract No. 06-206-13-59 07-201704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 7% 49% 07-LA-60-29.4/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 07-20-06 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02214 Total Estimate This Estimate 1. Contract Itms Without Mobil. 828,885.28 462,995.28 2.a. Extra Work 2,984.42 2,984.42 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 831,869.70 465,979.70 5. Mobilization 6. Total Work Completed 831,869.70 7. Deductions 8. a.Contract Retentions -83,186.97 -46,597.97 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 748,682.73 419,381.73 10. Reduction Amt to Escrow 11. Payment to Escrow 83,180.00 12. Net Pymt. this Estimate 419,381.73